Site Progress – March 2016

Following the on-land groundworks, Thomas Armstrong have been working in the water completing the installation of sheet piling to form a new lake edge. The sheet piling stretches from the boatyard area where the slipway will be located, all the way to the historic dock wall edge. The areas of sheet piling will form some of the structure needed to support the new boathouse, this will be longer than the old building and is a portal frame design creating the maximum roof height for boats on display in the water.