News | Page 2 | Windermere Jetty

News

Site Progress - April

Further progress has been made on the jetties and boardwalk installations that were under construction last month including the heat pump installation beneath the main jetty.

Internally mechanical and electrical first fix is ongoing throughout the buildings including preparing the main exhibition space and reception area for the underfloor heating system that will be laid soon.

Esperance Programme - Shop 'til you drop

In November 2016 we set a group of GCSE students at Queen Elizabeth School, Kirkby Lonsdale, with a challenge. To research Windermere Jetty and its collection to find inspiration for a product that could be sold in the Museum’s shop. The product had to be suitable for 6-9 year old children and be priced accordingly. The students were to make prototypes of their products and all products were judged at the final session, just before the Christmas holidays.

Site Progress - March

Progress continues on from last months update, with the focus on constructing the external walls and roofs to all of the buildings in preparation for the final cladding finish to begin installation next month.

The main jetty is under construction and divers have now installed the lake source heat pump beneath. Much like a ground source heat pump, this will use energy from the water to heat the buildings giving the museum excellent sustainability credentials.

Site Progress - February

All of the copper roofs to the buildings are now almost finished as the final and largest roof to the exhibition building is nearing completion. With the external walls that have been constructed over the last few weeks, the space is beginning to take shape and the incredible backdrop to the museum collection is in full focus.

Site Progress - December

Thomas Armstrong has been able to take full advantage of the mild winter weather building up the walls of the café, learning space and reception. The copper roof has been completed to the learning centre building and the cladding specialists have moved on to covering the reception roof. The structural wall system has also started on the main exhibition building, the largest of the buildings, beginning to enclose the space and frame more of the views out to the lake.